Ilford, London

Knock-through, new kitchen, flooring and lighting throughout the ground floor.

This is sample content created by the Lymo demo importer. Replace it with your own project description, photos and milestones.

Project progress 100% complete

  1. Design & specificationCompleted · 22 Jul 2026
  2. Strip-outCompleted · 3 Aug 2026
  3. First fixCompleted · 15 Aug 2026
  4. PlasteringCompleted · 27 Aug 2026
  5. Fit-out: units, tiling, flooringCompleted · 8 Sep 2026
  6. Snagging & handoverCompleted · 20 Sep 2026